A project can be within its approved budget and still be in trouble.
In engineering and project management, we often monitor expenditure, purchase orders, and completion percentages. But spending money doesn't necessarily mean we're making progress.
This is where Earned Value Management (EVM) becomes valuable.
Table of Contents
Understanding the Three Key Metrics
EVM integrates scope, schedule, and cost to measure project performance against an approved baseline.
It starts with three measurements:
Planned Value (PV): The budgeted value of work scheduled.
Earned Value (EV): The budgeted value of work actually completed.
Actual Cost (AC): The actual cost incurred for work performed.
Earned Value measures the budgeted value of work completed, rather than the actual cost incurred.
A Practical Six-Month Engineering Project
Consider a refrigeration system upgrade with an approved project budget of $1,000,000 and a planned duration of six months.
During planning, the project manager develops the Work Breakdown Structure (WBS), schedule, and time-phased cost baseline.
At each reporting date, the project manager compares cumulative PV, EV, and AC.
Month | PV | EV | AC |
|---|---|---|---|
1 | $100k | $90k | $110k |
2 | $250k | $220k | $260k |
3 | $450k | $380k | $430k |
4 | $650k | $590k | $680k |
5 | $850k | $800k | $900k |
6 | $1,000k | $1,000k | $1,100k |
All figures are cumulative and measured at the end of each month.
Earned Value Management: Comparing Planned, Earned and Actual Costs
The following EVM S-curve illustrates project performance throughout the six-month period.

The blue line (PV) represents the approved plan, the green line (EV) shows the budgeted value of completed work, and the red line (AC) shows actual costs.
Comparing these values allows project managers to evaluate cost and schedule performance.
Understanding Month 1: A Practical WBS Example
Consider the Mechanical Installation work package, with an approved budget of $100,000 and scheduled for completion by the end of Month 1.
However, the project manager confirms that only 90% of the installation is complete, while actual labour, materials, and contractor costs have already reached $110,000.
Metric | Value | What it means |
|---|---|---|
Planned Value (PV) | $100,000 | 100% of the work was scheduled |
Earned Value (EV) | $90,000 | 90% of the budgeted work was completed |
Actual Cost (AC) | $110,000 | Actual cost incurred to date, with 90% of the work completed |
The project has already incurred $110,000 to complete work budgeted at $90,000, with 10% still unfinished.
The remaining work will carry over into Month 2, potentially increasing the final cost.
This is why monitoring expenditure alone can be misleading.
Turning Numbers Into Better Decisions
Using the Month 1 figures:
Cost Performance Index (CPI) = EV / AC = 0.82
Schedule Performance Index (SPI) = EV / PV = 0.90
Cost Variance (CV) = EV − AC = −$20,000
Schedule Variance (SV) = EV − PV = −$10,000
What does this tell us?
The project is experiencing cost inefficiency and has completed less work than planned.
For every $1 spent, the project has earned approximately $0.82 of budgeted work value.
The negative schedule variance indicates that less work has been completed than scheduled, although it doesn't necessarily mean the project is 10% late in calendar time.
By Month 6, all planned work has been completed, but the final cost is $1.1 million — $100,000 above the approved budget.
From Measurement to Action
EVM should be established during Planning, when the performance measurement baseline and progress measurement methods are defined.
During Monitoring and Controlling, project managers use EVM to investigate variances, assess forecasts, and determine corrective actions.
Progress should be measured objectively through completed deliverables, verified installations, or approved milestones.
This Week's Reflection
When reviewing your projects, are you measuring actual progress against the approved baseline, or primarily tracking expenditure?
Are your performance reports helping you make decisions, or simply telling you what has already happened?
P.S. If we haven't connected yet, let's connect on LinkedIn and continue the conversation about project management and engineering.
Want more practical insights? Subscribe to The Saturday Mindset and receive the newsletter in your inbox every Saturday.
Thanks for reading, and until next Saturday!